Executive Summary
Generated July 30, 2026
Energy & Utilities
GE Vernova
Strategic importance is our editorial rating of how central this entity is to the technology landscape we track; confidence reflects how well-sourced and current the underlying evidence is.
2
Chokepoint Score
2 other entities structurally depend on this one
Accelerating
Activity
1 recorded change in the last 90 days
Steady
Momentum
insider filing activity unchanged since last check
Headquarters
Cambridge, Massachusetts, USA
Website
Employees
75,000 (2026, approximate)
Founded
2024
Listing
GEV · NYSE
Market Cap
$251.25B
Revenue (TTM)
$41.37B
Price
USD943.38 (-12.55%)
Market data as of Jul 29, 2026, 11:25 AM · Source: Yahoo Finance (delayed). Not investment advice.
Overview
A power generation and grid equipment manufacturer whose heavy-duty gas turbines are sold out through 2030-2031 amid surging AI data center demand, with Q1 2026 total orders up 71% year-over-year to $18.3 billion and electrification-segment data center equipment orders alone reaching a record $2.4 billion, exceeding all of 2025's total. Gas turbine pricing has risen up to 300% over three years as AI and data center load now makes up roughly 20% of GE Vernova's gas turbine backlog.
Strategic Connections
- Microsoft Azure: Microsoft ordered seven GE Vernova gas turbines for a roughly 2.7 GW Texas data center campus (Project Kilby), with first power targeted for 2028.
- Data Center Power & Cooling: GE Vernova's heavy-duty gas turbines, sold out through 2030-2031, are a primary bottleneck and enabler for AI data center power buildout.
- Siemens Energy: GE Vernova competes with Siemens Energy in heavy-duty gas turbines and grid equipment for AI data center power.
Strategic Risks
- Gas turbine manufacturing capacity is a hard physical bottleneck that cannot scale as fast as AI data center demand
- Customer concentration risk among a handful of hyperscalers driving the bulk of order growth
Future Outlook
- Backlog sold out through 2030-2031 provides multi-year revenue visibility
- Continued pricing power as gas turbine capacity remains the binding constraint on new AI data center power
- Expanded Niskayuna research campus expected to support next-generation turbine and grid technology development
Sources
4 sources, 79% average source confidence — full citations in the Full Analyst Report.
Generated by InsightNodes — Technology Intelligence Platform. This report reflects sourced, evidence-backed information as of the dates cited above and is not investment advice.
Viewing the Executive Summary — switch to the Full Analyst Report.