Khazna Data Centers
The UAE's largest data center operator, a G42 subsidiary running roughly 30 operational facilities with a further 1-gigawatt AI-capacity expansion underway. In 2025-2026, Khazna became the delivery vehicle for Microsoft's UAE build-out (a 200-megawatt Azure/AI expansion within a $15.2 billion multi-year commitment) and combined 12 data centers with telecom group e&'s assets into a new joint venture positioned as the country's largest data center provider.
Sources
Every claim traced to a primary source — evidence, recent activity, and insider filing behavior, all in one place.
Evidence
2 sources · 67% avg. source confidence
- Data Center Dynamics — Khazna unveils 1GW UAE AI data center expansion66% source confidence
- Microsoft / TechInformed — Microsoft and G42 announce 200MW UAE data center expansion via Khazna68% source confidence
Dependency Map
What Khazna Data Centers depends on below, and who depends on Khazna Data Centers above — click any node to make it the new center, 5 levels deep.
Connection type
Click any node to make it the new center. Scroll to zoom, drag to pan.
The Story So Far
Auto-generated from this entity's dated milestones, relationship updates, and sourced evidence — not AI-written, just sorted.
Khazna Data Centers's Timeline
A sourced, dated history of Khazna Data Centers's key moments — founding to present.
Oct 2025 · Unveils 1GW expansion plan
Khazna unveiled a 1-gigawatt AI data center capacity expansion plan, building on its existing roughly 30 operational facilities across the UAE.
Nov 2025 · Microsoft 200MW expansion
Microsoft and G42 announced a 200-megawatt UAE data center capacity expansion to be delivered by Khazna, part of Microsoft's broader $15.2 billion UAE commitment through 2029.
Apr 2026 · Breaks ground on 60MW UAE sites
Khazna broke ground on two new UAE data centers with a combined 60 megawatts of capacity, expected to complete through 2026.